EV (Electric Vehicle) charging installation requirements - 15 questions from a large question bank (reference can be made to BS7671 regulations book, On-Site guide, Electrical Design Guide and Code of Practice: Vehicle Charging Equipment Installation publications when completing this exercise).
At what value of maximum demand for the installation are you required to inform the DNO before installing a new EV charging point
30 amps
40 amps
50 amps
60 amps or above
If the supply cable feeding the installation is a 'looped supply', you need to
Inform the DNO within 28 days after installation of the new EV charging point
Inform the customer that they have a looped supply cable installed
Not install the new EV charging point and contact the DNO
Ask the customer to contact the DNO after the new EV charging point has been installed
If the value of the maximum demand for the installation is below 60 amps, after installing a new EV charging point you need to contact the DNO and inform them within
7 days
14 days
28 days
6-months
The PME notice on an installation supply cut-out would indicate that the earth arrangement is
TN-C-S
TN-S
TT
TN-C
What is meant by the abbreviation ENA
Energy Network Association
Energy Notification Authority
EV Network Association
EV Notification Authority
When installing a new EV charging point, avoid protecting the EV charging circuit with a
type ‘B’ RCBO
type ‘A’ RCBO
type ‘AC’ RCD
MCB
The circuit supplying a new EV charging point does not require 30mA RCD protection if it is
Surface clipped PVC flat profile cable
Surface clipped PVC flat profile cable chased into a wall at a depth of less than 25mm
PVC flat profile cable chased into a wall at a depth of less than 35mm
PVC flat profile cable chased into a wall at a depth of less than 40mm
An EV application form for the ENA requires electrical installation details about the
Installation address, number of phases, maximum demands and the age of the EV to be used
Earthing arrangement, supply voltage, the manufacturer of the EV charging point and the installation address
Supply voltage, maximum demand, earthing arrangement and installation address
Age of the EV to be used, the manufacturer of the EV charging point, the installation address and the supply voltage
When installing a new dedicated circuit for an EV charging point best practice requires
The circuit is protected by an AC-type RCD
A separate consumer unit is installed for the new EV charging point
The cable run is 5m or less for the new EV charging point
The new EV charging point is installed at least 2m above finished floor level.
To monitor the incoming supply current, which conductor do you connect the current transformer to
The line conductor in the cable that feeds the new EV charging point
The neutral conductor in the cable that feeds the new EV charging point
The neutral conductor of the meter tail feeding the installations' consumer unit feeding the property
The line conductor of the meter tail on the consumer’s side of the kWh meter.
When connecting a current transformer to a conductor, it’s important that the arrow on the current transformer points
Upwards
Downwards
Into the installation away from the kWh meter
Outwards from the installation and away from the kWh meter
The largest rating of the cut-out fuse for a single phase domestic dwelling is
100A
80A
60A
30A
Which one of the following earthing arrangements is NOT a commonly used for a domestic dwelling in the U.K.
TN-C
PME
TT
TN-S
If the cable supplying a new EV charging point requires RCD protection at 30mA or less, the installer should take into consideration the
Selectivity
Maximum demand
Diversity
The IP rating of the charging point
When installing a new dedicated circuit for an EV charging point, best practice requires
The circuit is to be protected by an ‘AC’ type RCD
An earth electrode resistance of 200 ohms is installed at the origin of the installation
A separate dedicated consumer unit is installed to supply the new EV charging point
The new EV charging point is fitted 2m from finished floor level.
Safe isolation of the supply must be carried out with an approved voltage indicating device that conforms to
BS7671
DS38
GS38
IP44
Why might a newly installed EV charging point cause an issue to an existing electrical installation
It's a large load connected for a short period of time
It's a large load connected for a long period of time
It's a small load connected for a long period of time
It's a small load connected for a short amount of time
Which of the following would NOT be a reason to contact the DNO regarding an electrical supply service head
Evidence of overheating
Damaged enclosure
Evidence of tampering
Service head securely fixed
When connecting a new EV charge point to a public network supply and it is suspected that the supply is not metered, what action needs to be taken
No action
Connect the charge point anyway
Contact the network operator and request a new connection
Contact the Local Authority (Council)
If the EV charging point is being connected to a landlord's electrical supply, what action is recommended
Contact the Local Authority (Council)
Confirm that the landlord has given permission for the charging point connection
Connect the charger up without making any enquiries
No special action is required
If the landlord refuses permission for the connection of a new EV charger point to their supply, what action should be taken
Suggest that the client considers legal action
Explain to the customer that the charger point cannot be installed
Connect the charger point to the supply anyway
Advise the client to contact the DNO to arrange a new supply
In which of the following publications will you not find methods for calculating maximum demand for an electrical installation
BS7671 Guidance Note 1: Selection and Erection
Code of Practice: Electric Vehicle Charging Equipment Installation
Electrical Design Guide
BS7671 On-Site Guide
Which Appendix of BS7671: Guidance Note 1 (Selection and Erection) contains information on calculating maximum demand for an installation
Appendix I
Appendix F
Appendix H
Appendix G
Which of the following is true regarding maximum demand from the appropriate appendix in BS7671: Guidance Note 1
It will give you the exact value of maximum demand
It is the only method you can use to calculate maximum demand
It is one acceptable method of calculating maximum demand
It will be appropriate for every type of installation
To find the current demand used by a load, which of the following basic formulas is correct
I=VR
I=P/V
I=V/P
I=PV
In previous BS7671: On Site guidance, the recommended value to assume for a general lighting service lampholder when determining maximum demand for an installation was
65W
30W
100W
150W
According to the Electrical Design Guide, the recommended value to assume for a general lighting service lampholder is
65W
30W
100W
150W
According to guidance, small loads such as electric clocks, shaver outlets etc can be ignored for the purposes of maximum demand if their rating is below
3A
230v
5W
5VA
The principle that not all electrical loads will be operating at the same time is known as
Discrimination
Selectivity
Coordination
Diversity
How much current should be added to the maximum demand calculations to make allowance for a 13A socket outlet on a cooker control unit
6A
13A
5A
10A
What percentage of the total lighting load will be taken into account for maximum demand for a residential property
50%
66%
75%
90%
If the maximum demand of an installation is greater then 60A when including a new EV charge point, which of the following applies
Approval from the DNO must be granted prior to the installation of the EV charge point
Installation of the EV charge point can go ahead and the DNO notified within 28 days
The installation of the EV charge point can be completed with no notification required
An upgrade to the supply should be requested from the DNO
Which part of regulation 722.411.4.1 applies for an EV charge point which electrically disconnects the electric vehicle from the live conductors and Earth if the voltage exceeds 253v or is less than 207v
(v)
(ii)
(iii)
(iv)
Before siting an EV charge point, Codes of Practice: Electric Vehicle Charging Equipment Installation recommends a survey to determine
Internet network connectivity
External influences
Risk of tampering
Structural integrity
Which of the following best describes the Code of Practice's recommendation for RCD protection for EV charge points
A stand alone RCD must always be provided
A stand alone RCD must never be used
Two RCDs in series should be provided
Manufacturer's instructions should be followed regarding RCD selection
Which section of BS 7671 details Electric Vehicle Charging Installations
Section 721
Section 722
Section 729
Section 730
Which of the following is the mode of charging where connection to the EV is via standardized socket outlets not exceeding 32A and 250v AC
mode 1
mode 2
mode 3
mode 4
The term used by BS 7671 to describe limiting the amount of current drawn into an installation is
Load curtailment
Load current
Limited current
Limiting curtailment
According to BS 7671, load shedding can be taken into account when considering which of the following
Diversity
Selectivity
Maximum Demand
Segregation
Placing the current transformer around an incoming Line conductor can help to
Control of all loads in the installation
Ensure the EV charge point won't overload the supply
Balance the current demand of the installation
Reduce the supply voltage to a safer level
If using a current transformer to limit the load current, what control criteria must be met
Hard wired and cloud managed
Wireless operation and cloud managed
Wireless operation and locally managed
Hard wired and locally managed
Which of the following is a correct statement in relation to charging an electric vehicle in an outside\outdoor environment
A PME earthing facility can be used as the sole means of earthing without any special precautions
A PME earthing facility must never be used as the means of earthing
A PME earthing facility can be used the means of earthing as long as certain other precautions are also in place
A PME earthing facility must be used as the main means of earthing without any special precautions
What does the abbreviation PME mean
Preventative Multiple Earthing
Protected Monitored Earthing
Protective Multiple Electrodes
Protective Multiple Earthing
What is the generally accepted minimum level of mains current that is harmful to a person
30mA
50mA
70mA
100mA
What is the voltage between CPC and Earth that the EV regulations require a device to disconnect a charging electric vehicle from the supply
25V
30V
50V
70V
According to part (iv) of regulation 722.411.4.1, what is the maximum voltage permitted between line and neutral before the protective device has to operate
207V
230V
240V
253V
According to part (iv) of regulation 722.411.4.1, what is the minimum voltage permitted between line and neutral before the protective device has to operate
207V
230V
240V
253V
If no RDC-DD is used in an EV charge point installation circuit, what type of RCD protection must be provided
Type B
Type A
Type F
Type AC
If an RDC-DD is used in an EV charge point installation circuit, what type of RCD protection can be used
Type AC or Type B
Type AC or Type F
Type AC or Type A
Type A or Type F
What does the abbreviation RDC-DD stand for
Residual direct current detection device
Remaining direct current detection device
Residual direct current detection delay
Remaining direct current delay detection
At what value of current must the RDC-DD disconnect the EV charge point from the mains supply
6mA
10mA
100mA
40mA
Which one of the following conditions applies when separate RDC-DD and RCD protection is used for an EV charge point circuit
The RDC-DD and the RCD must both be installed in the charging unit
The RDC-DD may be installed in the charging equipment and the RCD upstream
The RDC-DD must be installed in the charging unit and the RCD in the consumer unit
The RDC-DD and the RCD must both be in the consumer unit
What is the minimum IP rating for EV charging equipment installed outdoors, to protect against the presence of water and solid objects
IP44
IP64
IP65
IP54
With reference to BS 7671, what is the minimum impact rating required for EV charging equipment installed in car parks and other public areas
IK10
IK07
IK09
IK08
With reference to BS7671, which one of the following is the mode of charging where connection to the EV is via dedicated electric supply equipment where the control pilot function extends to control equipment in the EV supply equipment
mode 1
mode 2
mode 3
mode 4
What percentage of the total lighting load will be taken into account for maximum demand for a small hotel
50%
75%
66%
90%
Which part of regulation 722.411.4.1 applies for an EV charge point which electrically disconnects the electric vehicle from the live conductors and Earth if the voltage between the c.p.c and Earth exceeds 70v due to an open circuit in the PEN conductor